The following statements have

The following statements have been made about planning and operational variances: (1) Planning and operational variances are calculated when it is necessary to assess a manager on results that are within his/her control. (2) Revised standards are required because variances may arise partly due to an unrealistic budget, and not solely due to operational factors. Which of the above statement(s) is/are true?
A、(1) only
B、(2) only
C、Neither (1) nor (2)
D、Both (1) and (2)



【参考答案及解析】
Both (1) and (2)