How is an overhead absorption rate calculated?
A、Estimated overhead ÷ actual activity level
B、Estimated overhead ÷ budgeted activity level
C、Actual overhead ÷ actual activity level
D、Actual overhead ÷ budgeted activity level
A、Estimated overhead ÷ actual activity level
B、Estimated overhead ÷ budgeted activity level
C、Actual overhead ÷ actual activity level
D、Actual overhead ÷ budgeted activity level
【参考答案及解析】
Estimated overhead ÷ budgeted activity level
Estimated overhead ÷ budgeted activity level