首页 习题正文

A manufacturing company uses t

A manufacturing company uses three processes to make its two products, X and Y. The time available on the three processes is reduced because of the need for preventative maintenance and rest breaks. The table below details the process times per product and daily time available: Process Hours available Hours required to make Hours required to make per day one unit of product X one unit of product Y 1 22 1.00 0.75 2 22 0.75 1.00 3 18 1.00 0.50 Daily demand for product X and product Y is 10 units and 16 units respectively. Which of the following will improve throughput?
A、Increasing the efficiency of the maintenance routine for Process 2
B、Increasing the demand for both products
C、Reducing the time taken for rest breaks on Process 3
D、Reducing the time product X requires for Process 1



【参考答案及解析】
Throughput is determined by the bottleneck resource. Process 2 is the bottleneck as it has insufficient time to meet demand. The only option to improve Process 2 is to improve the efficiency of the maintenance routine. All the other three options either increase the time available on non-bottleneck resources or increase demand for an increase in supply which cannot be achieved.
版权声明

本文仅代表作者观点,不代表本站立场。
本文系作者授权发表,未经许可,不得转载。

本文链接:https://scpro.cn/v/92a8d08e89a8416b.html