CreatingWBSmeanssubdividin(2010年下半年信息系统项目管理师上午综合知识真题解析)
Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the( )level.
A.independent resource
B.individual work load
C.work milestone
D.work package
参考答案: D
参考解析:正在整理中,欢迎在文下评论区提供答案解析,谢谢!