Aprojectmanagerbelievestha(2010年上半年系统集成项目管理工程师上午综合知识真题解析)
A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should( ).
A.assign change tasks to project members
B.call a meeting of the configuration control board
C.change the scope baseline
D.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
参考答案: D