无(2017年上半年系统集成项目管理工程师上午综合知识真题解析)
The key benefit of( )is that it provides guidance and direction on how the project costs will be managed throughout the project.
A. Plan Cost Management
B. Control Cost
C. Estimate Cost
D. Determine Budget
参考答案: A