( ) is a method of constructing a project schedule network diagram that uses boxes or rectangles,referred to as nodes,to represent activites and connects them with arrows that asow the dependencies.(

( ) is a method of constructing a project schedule network diagram that uses boxes or rectangles,referred to as nodes,to represent activites and connects them with arrows that asow the dependencies.(2005年上半年信息系统项目管理师真题解析)
A、PDM
B、CPM
C、PERT
D、AOA






答案:A
参考解析:正在整理中,欢迎在文下评论区提供答案解析,谢谢!