Ohyes Co uses activity based costing and produces three products called ET, TT and GT. Ohyes Co expects to incur the following indirect production costs next year. What is the cost per purchase order?



【参考答案及解析】
Cost per machine set-up = Material ordering costs / total number of purchase orders Total number of purchase orders = (40 × 3) + (20 × 2) + (55 × 4) = 380