Yourprojectisbehindschedul(2012年上半年信息系统项目管理师上午综合知识真题解析)
Your project is behind schedule due to conflict between team members .Haring resolved the conflict, to get the project back on schedule,you should consider ( ).
A、crashing the Schedule
B、performing resource leveling
C、conducting reverse resource allocation Scheduling
D、utilizing the critical chair resources
参考答案: A
参考解析:正在整理中,欢迎在文下评论区提供答案解析,谢谢!