()isthebudgetedamountforth(2005年下半年信息系统项目管理师上午综合知识真题解析)
( )is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.
A.Planned value
B.Earned value
C.Actual cost
D.Cost variance
参考答案: B