Your company CEO just sent you an E-mail asking you to make a … on your project , which has been in progress for 10 months , to all Identified internal and external stakeholders. He scheduled the presentation for next Monday.You expect more than 50 people to attend. The first step in preparing the presentation is to ( ).
A. define the audience
B. determine the objective
C. decide on the general form of the presentation
D. plan a presentation strategy
参考答案: B