Projectmanagerbelievesthat(2012年上半年系统集成项目管理工程师上午综合知识真题解析)
Project manager believes that modifying the project scop may provide added value for the customer.The project manager should( ).
A.change the scope baseline
B.contact the customer to determine if the change adds value
C.call a meeting of the change control board
D.change the project's objectives
参考答案: B
参考解析:正在整理中,欢迎在文下评论区提供答案解析,谢谢!