estimateactivitydurationsi(2018年上半年信息系统项目管理师上午综合知识真题解析)
Estimate Activity Durations is the process of estimating the number of work periods to complete indivities with estimated resources . The tools and technques is not including().
A、expert judgment
B、analogous estimating
C、requirements traceability matrix
D、three-point estimating
参考答案: C