TheEstimateActivityResourc(2008年下半年信息系统项目管理师上午综合知识真题解析)
The Estimate Activity Resource process is closely coordinated with the( )process.
A. Estimate Costs
B. Sequence Activities
C. Plan Communications
D. Conduct Procurements
参考答案: A