Bortamord anticipates that a 9

Bortamord anticipates that a 90% learning curve will apply to the production of a new item. The first item will cost $2,000 in materials, and will take 500 labour hours. The cost per hour for labour and variable overhead is $5. You are required to calculate the total cost for the first unit and for the first eight units.